Repair of structures
The objective of this investment is to review and repair the viaducts, bridges and footbridges present in the road network of the Community of Madrid.
The repair of structures is one of the five major axes that are part of the new 2018-2021 Road Maintenance Strategy. The structure maintenance and repair contract will allow the more than 1.120 viaducts, bridges and footbridges present in the region's road network to be reviewed and left in the best conditions with a budget of €21,82 million.
Repair of running structures
LONG BRIDGE OF ARANJUEZ OVER JARAMA RIVER
This action consists of the repair of those deteriorated or damaged elements of the superstructure, piers, foundations, vaults and parapets of the Long Bridge of Aranjuez, located at km 2,8 of the M-305 road, directly related to the capacity of service of the bridge, it will also act on the origin of the pathologies described: waterproofing, drainage system, pavement and sidewalks.
Execution period: 6 months.
PEDESTRIAN FOOTBRIDGE OVER THE M-607 PK 15,800
The action consists of the improvement and repair of the pedestrian walkway on the M-607 road that gives access to the UAM at pk 15,800.
The expected execution period is one month from July 8, 2019.
PEDESTRIAN FOOTBRIDGE OVER THE M-607 PK 23,000.
The action consists of the improvement and repair of the pedestrian walkway on the M-607 highway at pk 23,000.
The expected execution period is three months from July 9, 2019.